Numerical - Calculate B.E.P capacity for given fixed cost & percentage of variable cost

Q.  Calculate B.E.P capacity if Fixed cost is Rs 50,000, percentage of variable cost is 66 2/3% and capacity is Rs 3,00,000.
- Published on 15 Sep 15

a. 25%
b. 30%
c. 50%
d. None of the above

ANSWER: 50%
 

    Discussion

  • Dhiraj Virmani   -Posted on 02 Dec 21
    Please upload the each and every question and answers with explanation because of without information is not understood the answer and your effects are not worth and helpful
  • Mayur   -Posted on 21 Sep 20
    Give ans
  • nana yaw   -Posted on 03 Feb 17
    please explain to me
  • Gurubrahmam   -Posted on 15 Dec 16
    Please upload the each and every question and answers with expiations

Post your comment / Share knowledge


Enter the code shown above:

(Note: If you cannot read the numbers in the above image, reload the page to generate a new one.)