Which of the following techniques give the best project estimate?

Options
- Bottom up estimating
- Parametric estimating
- Analogous estimating
- Three point estimating


CORRECT ANSWER : Bottom up estimating

Discussion Board
Explanation-

Bottom-up method uses a detailed work breakdown structure, and is best for projects estimates.

Sapna Ambadkar 03-16-2017 07:39 AM

Write your comments

 
   
 
 

Enter the code shown above:
 
(Note: If you cannot read the numbers in the above image, reload the page to generate a new one.)


Advertisement