To which phase will training cost fall?

Options
- Failure
- Prevention
- Build
- Appraisal


CORRECT ANSWER : Prevention

Discussion Board
Training cost

Answer: Prevention

Solution: Preventive: It includes those activities that are used to reduce the defects like: statistical process, training etc.
Appraisal: It includes those activities that are used to identify the defects before the product go live.
Failure: If any product or software is failing to satisfy the requirement.
Therefore, Prevention is correct answer.


Rohit Srivastava 07-22-2014 06:52 AM

Write your comments

 
   
 
 

Enter the code shown above:
 
(Note: If you cannot read the numbers in the above image, reload the page to generate a new one.)