The difference between contract closure and administrative closure is that

Options
- Contract closure involves customer signature
- Contract closure can be done more than once for each contract
- Contract closure occurs before administrative closure.
- Contract closure is really not required when administrative closure can close projects with contracts


CORRECT ANSWER : Contract closure occurs before administrative closure.

Discussion Board
Explanation-

In administrative closure, close Project or Phase process is done when all the work has been verified, delivered, and accepted by the customer.
Contract Closure:
A contract is closed upon reaching the end of the contract, or when a contract is terminated before he work is completed.