Umbrella activities- Features, Properties - Software Management

Q.  Choose the correct option according to given below statement.

Statement 1: Umbrella activities are independent of any one framework activity and occur throughout the process.
Statement 2: software quality assurance, software configuration management are umbrella activity.
Statement 3: software quality assurance, software configuration management are not umbrella activity.

- Published on 19 Oct 15

a. Only statement 1 is correct.
b. Statement 1 and statement 2 are correct.
c. Only statement 3 is correct.
d. Statement 1 and statement 3 are correct.

ANSWER: Statement 1 and statement 2 are correct.
 

    Discussion

  • Prajakta Pandit   -Posted on 21 Aug 15
    - Umbrella activities are the set of tasks that include some activities related to software engineering process. Such as,
    - Quality assurance
    - Risk Management
    - Configuration Management
    - Project Management
    - Requirement Management