Q.  P, Q and R take a job for Rs. 640. P and Q together finish 2/5thof the work and rest is done by R alone. What is the share of R?
- Published on 10 Mar 17

a. Rs. 256
b. Rs. 420
c. Rs. 340
d. Rs. 384

ANSWER: Rs. 384
 