You are managing a project with an EV of Rs.20,000, PV of Rs.15,000 and AC of Rs.10,000. How would you best describe this project?

Options
- The project is ahead of schedule and within its budget
- The project is behind schedule and within its budget
- The project is ahead of schedule and over its budget
- The project is behind schedule and over its budget


CORRECT ANSWER : The project is ahead of schedule and within its budget